Bahrain announces the bid results for Water Transmission Facilities projects

Bahrain’s Electricity & Water Authority (EWA) announces the bid results for the water transmission facilities for East Hidd and South Bahrain (Madinat Khalifa).

Water Transmission Facilities for South Bahrain (Madinat Khalifa):

Turnkey Contract Package covering all the Water Distribution Station and the associated Transmission pipeline works for South Bahrain Housing Development.

The Contract comprises the construction of 2 No. RCC Storage Tanks of minimum 5 Million Gallons capacity each, a fully automated Distribution pumping station of 10 million gallons per day ultimate capacity.

A total of five (5) bidders has submitted the proposals. Faisal Co. for Electrical & Mechanical has submitted the lowest bid of BHD 11.8 million.

Water Transmission Facilities for East Hidd:

Turnkey Contract Package covering the permanent Distribution Station Works at East Hidd Housing Development.

The contract comprises partially buried RCC Storage Reservoir of Minimum 2 Million Gallons Capacity and an associated fully automated Distribution Pumping Station with variable speed pumps of about 5 Million gallons per day ultimate Capacity and other associated facilities.

A total of four (4) bidders has submitted the proposals. Faisal Co. for Electrical & Mechanical has submitted the lowest bid of BHD 6.4 million.

The two projects are funding by Saudi Fund for Development.

To Promote your Products and Services on SaudiGulf Projects, please visit "Advertise" Section

1 Trackback / Pingback

  1. Project awarded for Water Transmission Facilities projects in Bahrain

Comments are closed.