As per the terms of the project, contractor will execute the works on lump sum turnkey basis for Engineering, Procurement and Construction for the Rehabilitation of 110/13.8kV Substation that was burnt due to fire incident.
Existing available Gas Insulated Switchgear and Power Transformers will be utilized for this project.
The project scope of works includes 13.8kV Switchgear, Protection & Control System, Substation Automation System, Telecom System, Civil Works and Electro-Mechanical Works.
Contractor needs to achieve the final acceptance of the works by 24 months from Contract Signing Date.
Hyundai Motor Manufacturing Middle East (HMMME), a joint venture between PIF and Hyundai Motor Company, hosted its groundbreaking ceremony in the recently announced King Salman …
East Pipes Integrated Company for Industry, Saudi Arabia announced in a statement that it has signed Multiple Contracts with NEOM. The total value of the …
Saudi Electricity Company (SEC) issued a tender for the “Construction of 380kV Transmission line between Al Aseelh (ASL) 380/132/13.8kV BSP and Shuqaiq Substation”. The location …
1 Trackback / Pingback
Comments are closed.