Saudi Electricity Company (SEC) received bidders proposals for the Installation of 132kV cables related to AL SHARAFIYAH and AL-HADA Substation in Riyadh.
Seven bidders has submitted the proposals. Saudi based construction firm, CEPCO has submitted lowest bid.
CEPCO submitted the price of SAR 110.9 million (USD 29.5 million).
Project scope of works includes Installation of 132kV Underground cable in order to connect the new substations with the network.
Total route length of the underground cable is approximately 32km.
***