Qatar General Electricity & Water Corporation (Kahramaa) invites Bids for the Power Evacuation From Dukhan Solar Project.
The Project is an EPC Contract for establishment of new 400/220/132kV Substation and upgrade / modifications of the existing substations Overhead Lines (OHL) and cables of 400kV, 220kV 132kV.
The project is divided into several packages as described below:
- Substations Package S1: New 400/220/132kV Substation.
- Package S2 & S3: upgrade of existing 400kV and 220kV substations and modifications in several substations.
- Cables Package C1: 220kV Cables.
- Overhead Lines Package OHL1: 400kV
- Package OHL2: 400kV
- Package OHL3: 220kV
- Package OHL4: 132kV
Kahramaa sets the bid submission date as 21 August 2025.
Earlier during September 2024, Qatar announces to build solar power plant in Dukhan area, with a production capacity of 2,000 megawatts. (read more)
With the addition of the new Dukhan Solar Power Plant, QatarEnergy’s portfolio of solar power projects in Qatar will reach a capacity of about 4,000 megawatts by the year 2030. This represents approximately 30% of Qatar’s total electrical power production capacity.