ELSEWEDY ELECTRIC awarded 400kV OHTL Project in UAE

ELSEWEDY ELECTRIC T&D announces that it has awarded Overhead Transmission line Project in UAE.

The Project was awarded by Abu Dhabi Transmission Company TAQA Transmission.

Scope of Works includes the full design, supply, and installation of 400kV LILO and conductor uprating works extending 53.8 kilometers, high-capacity 132kV overhead line circuits, and three underground cable circuits. The Project is related to the ADCG Grid Station under the ADNOC Ruwais LNG development.

The duration of the project is 30 months.

The company stated that, this contract further strengthens our contribution to the UAE’s energy infrastructure by delivering reliable and advanced transmission solutions.