Alfanar awarded $11million 380kV Reactors Project for Qaisumah region

Saudi based Alfanar Construction Company secured the project “Installation of 380kV Reactors at Qaisumah 380/115kV Substation.

The location of project is in Qaisumah , eastern region of Kingdom of Saudi Arabia.

The project has been awarded by Saudi Electricity Company (SEC). The contract value of the project is SAR 41.4 million (1$=3.75 SAR)

Project Scope of work includes Installation of 380kV Line Shunt Reactors with the required 380kV Hybrid Gas Insulated Switchgear (HGIS), Neutral Grounding Reactors, Surge arresters, 380kV cables, civil works at existing Qaisumah 380/115kV Substation including complete protection, metering, control, communication and modification.

The new equipment installed shall be equipped with Substation Automation System (SAS) and will be remotely controlled from the Power Control Center (PCC) through SCADA system, communication System and gateway.

The total duration of Project is eighteen (18) months.

The contractor shall perform the project on lumpsum turnkey basis, includes the design, engineering, material procurement, quality management, factory inspection/testing, transport and delivery to site, construction, site inspection, testing and commissioning, and all associated work and services until final handing over of the project.

Read Also: Alfanar submits $22.5million for 380kV Khasm Al Aan Substation expansion

***