Saudi Water Partnership Company (SWPC) announces the Preferred Bidder and Reserved Bidder for Al-Haer Independent Sewage Treatment Plant Project (ISTP Project).
Al Haer ISTP will have a total ultimate treatment capacity of 200,000 m3/day. It will be located in the city of Riyadh in Riyadh Province, Saudi Arabia.
As a part of SWPC’s objectives to enhance the utilization of Treated Sewage Effluent, the project includes TSE re-use system consisting of 32 km transmission pipeline with a capacity of 400,000 m3, pumping station and TSE reservoir tanks with a capacity of 200,000 m3.
Following is the Bidders’s Levelized Cost:
- Preferred Bidder – Miahona and BESIX Consortium – 1.9407 SAR/Cu.m
- Reserved Bidder – Acciona and TAWZEA Consortium – 2.2041 SAR/Cu.m
Earlier, during June 2023, Five Bidder submitted the proposals. (read more)
As per the tender notification, SWPC announced that it will conduct a competitive process to select a developer or developer consortium for the development, financing, engineering, procurement, construction, implementation, ownership, operation, maintenance and transfer of the Project, together with associated infrastructure and facilities.
Under a 25-year Sewage Treatment Agreement (STA) with SWPC, a project company is to be incorporated to develop the Project and will treat the entire sewage capacity supplied by SWPC.
SWPC’s obligations under the STA will be supported by a credit support agreement from the Government of Saudi Arabia.
SWPC is being advised by:
- KPMG Professional Services as as Financial and Lead Advisor
- White & Case LLP as Legal Advisor
- Future Water and Power Consulting as Technical Advisor.
The project targets the commercial operation by the third quarter of 2026.