Saudi utility company announces the bid results for Airport Substation

Saudi utility company, Royal Commission for Jubail & Yanbu announces the bid results for “Construction of 34.5/13.8kV Airport Substation”. The location of substation is located in Jubail area, eastern region of Saudi Arabia

A total of eleven (11) companies has submitted the proposal. Saudi based  construction company, Al Nowaiser for Trading and Contracting has quoted the lowest price of SAR 78.6 million.

Project scope of work includes 34.5kV Switchgear, 13.8kV Switchgear, 33/13.8kV, 20/25 MVA Power Transformers, 5MVAr Capacitor bank, Protection & Control System, SCADA System, Telecommunication System and other auxiliaries.

Project scope of work also includes installation of 34.5kV Cable between new substation to remote end.

The project will be constructed as per Saudi Electricity Company specifications.

Total project duration is three (3) years.

For complete results and scope of work, please contact us.