Al Sharif awarded $52.7million Saad Solar PV 380/132kV Substation

Al Sharif Group for Contracting signed a EPC contract for the Construction of Saad Solar PV 380/132kV Substation. The Project location is in Saad, around 85km from Riyadh.

The value of signed contract is SAR 197.7 million (USD 52.7 million).

The Project was awarded by Saudi Electricity Company (SEC).

SEC received bidders proposals during November 2020 (read more)

Saad Solar PV 380/132kV Substation will be interconnected to the proposed Renewable Energy (Solar) Power Plant at Saad. The Tender was issued during September 2020 (read more)

The Planned Capacity of the Saad Solar Power Plant is 300MW. REPDO already released the tender for Saad Solar PV IPP (read more)

Project involves the construction a new indoor 380/132 kV Gas Insulated Substation, named as Saad Solar PV 380kV/132 kV Substation.

The Substation consist of major equipment of 380kV Gas Insulated Switchgear (GIS), 132kV GIS, 302/402/502MVA, 380/110/13.8kV power transformers, 13.8kV Switchgear, 2.5MVA, 13.8kV/400V-230V Station Service Transformers, 13.8kV Grounding Transformers, Control/Protection System, Substation Automation System (SAS), Communication System, Fire Detection/Alarm & Safety and Fire Protection System, Civil/Structural works & Mechanical works, HCIS Security System.

The Contractor will perform on Lump sum turnkey basis, the design, engineering, materials procurement, quality management, factory inspection/testing, transport and delivery to site, installation, construction, site inspection, testing and commissioning.

Contractor needs to achieve the final acceptance of the works by 26 months from Contract Signing Date.
***