thyssenkrupp Signs Contract to Install Over 2GW Electrolysis Plant for Air Products in NEOM

Air Products announced in a statement that it has awarded thyssenkrupp Uhde Chlorine Engineers a contract to supply a more than two-gigawatt (2 GW) electrolysis plant for one of the world’s largest green hydrogen projects at NEOM in Saudi Arabia.

Under this contract, thyssenkrupp will engineer, procure and fabricate the plant based on their large-scale 20 megawatt (MW) alkaline water electrolysis module.

Upon commissioning, the project partners ― NEOM, ACWA Power and Air Products (NEOM Green Hydrogen Company) ― will operate the facility, which will produce hydrogen to be synthesized into carbon-free ammonia for export exclusively by Air Products to global markets. Engineering and procurement activities have been initiated, and the start of production is scheduled for 2026.

In July 2020, Air Products, together with ACWA Power and NEOM, announced the signing of an agreement for world-scale green hydrogen-based ammonia production facility powered by renewable energy. (read more)

thyssenkrupp was selected by its strategic partner Air Products early in the project as technology supplier and has worked intensively on early engineering and project development.

The signing of the project contract is a key milestone of both companies’ joint effort over the past year to use their complementary technology, engineering and project execution strengths to develop green hydrogen production facilities. The realization of the project leverages thyssenkrupp’s large-scale technology supporting Air Products’ development of green hydrogen for sustainable transportation, chemicals and power generation statement mentioned.