Saudi Arabia’s Ministry of Housing (MOH) announces the bid results for “Construction of Rabigh Housing 110/13.8 kV Substation”.

The project location is in Rabigh, Western region of Kingdom of Saudi Arabia.

A total of thirteen bidders has submitted the proposals. Saudi based Construction Company, Al Osais Contracting Co. (Al Osais) has submitted the lowest bid.

Al Osais has submitted the price of SAR 54.5 million.

Project Description:

To meet with the expected power requirement of Rabigh Housing Project, Ministry of Housing invited the tender for construction of 110/13.8kV Substation.

The project scope of work includes the following major material:

  • 110kV Gas Insulated Switchgear
  • 50/67MVA, 110/13.8kV Power Transformers
  • 13.8kV Switchgear
  • 13.8kV, 7MVAr Capacitor Bank
  • 500kVA, 13.8kV/400-230V Station Service Transformers
  • MV Power Cables and Terminations,
  • AC/DC Auxiliary Power Supply,
  • Surge Arresters
  • Control/Protection System,
  • Substation Automation System (SAS)
  • Communication System
  • Fire Detection/Alarm and Safety and Fire Protection System
  • Civil/Structural works and Mechanical works

Project scope of work also includes extension of existing 110kV GIS by two bays at Rabigh-2 Substation.  Additions/modifications of Protection, Control system at Rabigh-2 Substation is also part of the contract.

The project will be implemented and supervised by National Grid SA.

The Contractor shall perform on Lump sum turnkey basis, the design, engineering, materials procurement, quality management, factory inspection/testing, transport and delivery to site, installation, construction, site inspection, testing and commissioning, all associated work and services until final handing over of new substation work in a satisfactorily working and operating condition.

Contractor needs to achieve the final acceptance of the works by 24 months from Contract Signing Date.

Earlier, Ministry announced the bid results for the high voltage cable connection tender, between the source substation and new substation. Saudi based Construction Company, Delta Company was the lowest bidder.(read more)

Read Also: Al Mashariq Submits the lowest bid of $16million for Umluj 110/13.8kV Substation

1 Comment

  1. Thank you for the information’s. Can you please help me contact/introduce to the winning company who has the project to get the details for us to Participate and quote for HV/EHV Underground Cable Jointing, Outdoor Termination, and Testing Projects. Thank you in advance for your support and cooperation.Note: Our company is doing worldwide projects, specialized on the said technical jobs with manpower certification up to 245kV. Contact info: E-mail me at: [email protected], whtasapp: +639357042761.. If you need Catalog, Company profile, Project List References, i’ll be happy to send. Thank you!

Comments are closed.