Saudi Electricity Company (SEC) awarded the contract for “Reinforcement of Rafeah-2 115/13.8 kV Substation”.
The project location is in Rafeah, eastern Region of Kingdom of Saudi Arabia.
The project has been awarded to Grupo Maessa Saudi Arabia Co. Ltd, a subsidiary of Spain based construction company, Grupo Maessa.
The value if signed contract is SAR 44,800,000 (1$=3.75 SAR).
Earlier, during November 2019, a total of seven bidders has submitted the proposals. Upon technical and commercial evaluation, the project has been awarded to contractor.
Project Description:
The project scope of work includes the following major material:
Rafeah-2 Substation:
- Three (3) bays of 115kV Gas Insulated Switchgear
- 13.8kV Switchgear
- 500kVA, 13.8kV/400-230V Station Service Transformers
- HV, MV Power Cables and Terminations,
- AC/DC Auxiliary Power Supply,
- Surge Arresters,
- Control/Protection System,
- Substation Automation System (SAS)
- Communication System
- Fire Detection/Alarm and Safety and Fire Protection System
- Civil/Structural works and Mechanical works
Project scope of work also includes Installation, testing & commissioning of 50/67MVA, 132/13.8kV power transformers. The material will be provided by SEC.
Additions/modifications of Protection, Control system at Ash Shumlul-2 Substation is also part of the contract.
Qaryat Al Ulya Substation
- One (1) bay of 115kV Gas Insulated Switchgear
- 13.8kV Switchgear
- 20MVAr STATCOM
- Control/Protection System modifications/Additions
- Substation Automation System (SAS) modifications/Additions
- Communication System modifications/Additions
The Contractor shall perform on Lump sum turnkey basis, the design, engineering, materials procurement, quality management, factory inspection/testing, transport and delivery to site, installation, construction, site inspection, testing and commissioning, all associated work and services until final handing over of new substation work in a satisfactorily working and operating condition.
Contractor needs to achieve the final acceptance of the works by 27 months from Contract Signing Date.
Read Also: Grupo Maessa Submits the lowest bid of $ 11.9 million for Rafeah-2 115/13.8kV Substation
In order to receive email notifications regarding our updates, please subscribe us.
***
SaudiGulf Projects – October 2025 Updates along with summary of Major Projects awards
Now available in PDF format!
Stay ahead with the latest project news, developments, and insights from across the Gulf.
For more details, please visit: Monthly Reports-October 2025