New 380kV and 132kV Substation tender issued for Riyadh

Riyadh Residential Development Company issued the tender for construction 380/132/13.8kV Substation and 132/13.8kV Substation.

The project location is in Riyadh, Central region of Saudi Arabia.

Project scope of work includes construction of new indoor 380/132/13.8kV Gas Insulated Substation. Major equipment includes, 380kV GIS, 132kV GIS, 502MVA Power Transformers, 67MVA Power Transformers, Protection and Substation Automation System, Telecommunication System, Civil works and Electro-mechanical works.

Project scope of works also includes the construction of new indoor 132/13.8kV Substation. Major equipment includes, 132kV GIS, 67MVA Power Transformers, Protection and Substation Automation System, Telecommunication System, Civil works and Electro-mechanical works.

Associated 380kV Underground cables and 132kV Cables between the new substations are part of the project. 

The Contractor shall perform on Lump sum turnkey basis, the design, engineering, materials procurement, quality management, factory inspection/testing, transport and delivery to site, installation, construction, site inspection, testing and commissioning, all associated work and services until final handing over of substation work in a satisfactorily working and operating condition.

At present bid submission date is 16 July 2020.

Read Also: SEC invite Bids for expansion of 380kV Substations

***

In order to receive email notifications regarding our updates, please subscribe us. 

For latest updates, follow us on  LinkedInFacebookTwitter, Instagram , PinterestYouTube

1 Comment

1 Trackback / Pingback

  1. SEC invites bid for 380/132/13.8kV Substation in Tabouk

Comments are closed.