Taiba Power Plant OHTL tender announced

Saudi Electricity Company (SEC) invites bid for the connection of 380kV Double Circuit Overhead Transmission Line (OHTL) from Taiba Power Plant to the network. The Project location is western region of Saudi Arabia.

The project involves the design and construction of  380kV OHTL from the Taiba Power Plant to various SEC’s substations.

Approximate route length of OHTL is 165 km.

The project involves using of 4-795 MCM ACSR/AW CONDOR conductor per phase and two (2) OPGW along the length of the new line.

The new OHTL will be installed on latticed steel tower in vertical configuration.

The Contractor shall perform on Lump sum turnkey basis, the design, engineering, materials procurement, quality management, factory inspection/testing, transport and delivery to site, installation, construction, site inspection, testing and commissioning, all associated work and services until final handing over of new OHTL work in a satisfactorily working and operating condition.

At present bid submission date is 10 March 2022.

Earlier during November 2021, The Saudi Power Procurement Company (SPPC) received expressions of interest (EOI) for Taiba combined cycle gas-fired Power Plant (read more)