NCC awarded $111.3m 380kV OHTL project

Saudi Electricity Company awarded the project, construction of 380kV Double Circuit Overhead Transmission Line (OHTL) between Jillah and Layla.

The Project has been awarded to Saudi based construction firm, National Contracting Company (NCC).

The value of the contract is SAR 417.4 (USD 111.3m).

Earlier, during November 2021, SEC received seven bidders proposals (read more)

The project involves the design and construction of 380kV OHTL to connecting the Jillah BSP and Layla BSP In central region of Saudi Arabia

Approximate route length of OHTL is 282 km.

The project involves using of 4-795 kcmil ACSR/AW CONDOR conductor per phase and two (2) OPGW along the length of the new line.

The new OHTL will be installed on latticed steel tower in vertical configuration.

The Contractor shall perform on Lump sum turnkey basis, the design, engineering, materials procurement, quality management, factory inspection/testing, transport and delivery to site, installation, construction, site inspection, testing and commissioning, all associated work and services until final handing over of new OHTL work in a satisfactorily working and operating condition.

Contractor need to complete the project activities within 25 months from the date of contract award.